Get a Quote for Secondary Dwelling Construction
Table of Contents
- What a Secondary Dwelling Quote Should Cover
- Granny Flat Quote Inclusions: What Belongs in Writing
- Granny Flat Site Costs and the Variables That Move Them
- Secondary Dwelling Permits and What They Add to the Quote
- Granny Flat Construction Timeline and How It Affects Price
- How to Compare Quotes Like for Like
- Step 1: Build a scope matrix before you read any total
- Step 2: Separate fixed from provisional, then compare
- Step 3: Check specifications, not just line-item names
- Step 4: Compare the energy and compliance commitments
- Step 5: Score the unknowns
- Step 6: Ask for the variation process in writing
- A worked comparison, in principle
- Quote Request Checklist Before You Shortlist Builders
- Frequently Asked Questions
Last Updated: October 17, 2026
What a Secondary Dwelling Quote Should Cover
A secondary dwelling is a self-contained home built on the same title as an existing house, sharing services and land but with its own kitchen, bathroom and entry. A quote for secondary dwelling construction prices a full building project, not a shed extension.
Below, we break down what belongs in a granny flat quote, how site costs move the number, what permits add, and how to compare builders fairly.
Granny Flat Quote Inclusions: What Belongs in Writing
Granny flat quote inclusions are the line items a builder commits to supply and install at the stated price. If it isn't written down, it isn't included, and it will come back as a variation.
At minimum, a written quote should list:
- Design, drafting and engineering documentation
- Building permit application and lodgement fees
- Site preparation and levelling allowance
Ask each builder to mark every item as included, excluded or provisional allowance. For guidance on what a compliant building contract must contain, the Victorian Building Authority guidance on domestic building contracts is the reference point.
Granny Flat Site Costs and the Variables That Move Them

Granny flat site costs cover preparing your block and connecting the new dwelling to services, the most common reason two quotes for the same design differ.
The variables that move them:
- Slope and excavation. A flat block needs minimal cut and fill. A steep rear section may need retaining walls, which are a separate structural cost.
- Access. If a crane truck or concrete truck cannot reach the build zone, you pay for pumps, conveyors or manual handling.
- Soil conditions. Reactive clay or rock close to the surface changes footing and slab design.
That is why a free site assessment matters before signing: a quote prepared from a plan alone cannot price ground conditions it has never seen.
Secondary Dwelling Permits and What They Add to the Quote
Secondary dwelling permits are the approvals needed before construction starts, adding direct fees and time-related costs to your quote.
In Victoria, a building permit is required for the construction itself. The Victorian Department of Transport and Planning guidance on planning permits sets out how the planning system applies, and your council's local provisions decide the detail.
What permits add to a quote:
- Building permit application and lodgement fees
- Planning permit fees where one is triggered
- Documentation and report costs, such as energy rating or soil reports
Ask every builder who is carrying the permit risk. If the quote excludes permit costs, budget for them separately and confirm who lodges the application.
Granny Flat Construction Timeline and How It Affects Price
Granny flat construction timelines run from design and approvals to handover, and that runway affects what you pay, but not as most owners assume. The build itself is usually the most predictable part. The uncertainty sits up front: documentation, approvals and site conditions, where two quotes for the same design can diverge by tens of thousands of dollars without either builder being dishonest.
A typical sequence, and what each stage does to the quoted number:
| Stage | What Happens | How It Moves the Price |
|---|---|---|
| Design and documentation | Drafting, engineering, energy rating, soil report | Fixed design fees; late changes trigger redesign fees and re-approval |
| Approvals | Building permit, planning permit if triggered, council referrals | Fees plus holding costs; a planning trigger can add months |
| Site preparation | Levelling, excavation, retaining, service trenching | The least predictable line; often carried as a provisional sum |
| Construction | Slab, frame, lock-up, fit-out | Fixed only if specifications and selections are locked before contract |
| Connections and inspection | Service connections, final inspection, handover | Usually a fixed allowance, but meter upgrades can vary |
Why the same build price produces different totals
Two builders can quote an identical construction figure yet land on very different totals because they assume different approval pathways and site conditions. A quote assuming a complying development pathway will be cheaper than one budgeting for a full planning permit, and if the planning trigger applies, the cheaper quote is the one that will vary. Ask each builder to state in writing the approval pathway assumed for your address and what happens to the price if that assumption is wrong.
The three timing costs owners underestimate
- Holding costs during approval. Rates, insurance and any bridging finance continue while you wait. A three-month approval delay is a real cost even though no builder invoices you for it.
- Price escalation between quote and contract. A quote is typically valid for a stated period, often 30 to 90 days. If approvals push signing beyond that window, ask whether the price is held or indexed.
- Weather and trade sequencing. Slab and frame stages are weather-sensitive. A quote that assumes a spring start may carry a different site-cost allowance than one assuming winter.
Indicative estimate versus fixed-price contract
This distinction matters most when comparing quotes. An indicative estimate is a builder's best guess from limited information, often prepared from a plan without a site inspection.
A quote prepared without a site inspection cannot be fixed-price on site costs, because the builder has not seen the ground, access or services, a limit of the information, not a criticism. The practical rule: treat any quote without a site inspection as an indicative estimate, and ask what converts it to a fixed price.
Book Your Free Site Assessment →
How to Compare Quotes Like for Like
Comparing quotes properly means normalising them before you look at the bottom line. Most owners do this backwards, reading totals first, then working out why they differ, by which point the headline number has anchored their judgement.
Use this framework on every quote you receive, it works whether you have two quotes or five.
Step 1: Build a scope matrix before you read any total
Turn the inclusions list from the first section into a spreadsheet with one column per builder, marking every line included, excluded or provisional, before you look at any price. The matrix shows at a glance which builders priced the same scope and which left gaps that will return as variations.
Step 2: Separate fixed from provisional, then compare
Total only the fixed items first for a like-for-like comparison of committed scope, then compare provisional allowances side by side. A low fixed total with a large provisional allowance for site costs is not cheaper, the builder has moved risk to you. A higher fixed total with no provisional sums offers more certainty, and that certainty has value.
Step 3: Check specifications, not just line-item names
"Concrete slab" means nothing without thickness, reinforcement and strength stated; "timber frame" without the framing specification; "kitchen fit-out" without appliance brands, bench material and cabinetry scope. Ask each builder to state the specification behind every major line item, and compare specifications rather than labels.
Step 4: Compare the energy and compliance commitments
Confirm the energy rating each builder commits to and who pays if it is not achieved. Confirm who lodges the building permit and who carries the risk if the permit is delayed or refused. These commitments are where quotes quietly differ, and they are rarely stated on the front page.
Step 5: Score the unknowns
A quote with three unresolved allowances is riskier than one with none, even at a higher headline price. Count the unknowns on each quote, provisional sums, excluded items, assumptions about access or soil, and treat that count as a risk score. Fewest unknowns usually means closest to the stated total.
Step 6: Ask for the variation process in writing
How changes are priced and approved tells you how the final number will behave. Ask each builder: what is the hourly rate for variations, is there a markup on variation materials, and how long does a variation take to approve? A builder who cannot answer these questions clearly is a builder whose final invoice will surprise you.
A worked comparison, in principle
Suppose Quote A has a lower fixed total but carries a provisional sum for site works and excludes service connections. Quote B has a higher fixed total, includes service connections and carries no provisional sums.
The lesson is not that the higher quote is always better. It is that the headline number is the least informative part of any quote until the scope has been normalised.
Quote Request Checklist Before You Shortlist Builders
Get your information together before requesting quotes. Builders quote faster and more accurately when the basics are ready, giving you comparable numbers instead of guesswork.
- Confirm your block size and the area available for a second dwelling
- Note the slope, access and any obvious site constraints
- Gather your title, plan of survey and any easement details
Granny X runs a free site assessment to confirm feasibility before quoting.
Frequently Asked Questions
What should a secondary dwelling construction quote include?
A complete quote should list design and drafting, engineering, secondary dwelling permits and council fees, site works, slab and frame specifications, cladding, roofing, windows, electrical and plumbing rough-ins, fit-out, and the builder's margin. Ask for a line-item breakdown rather than one lump sum. Confirm whether GST is included, what provisional sums apply, and which items sit outside the contract as owner-supplied. A quote that names materials and brands is easier to compare than one that only lists categories.
Do granny flat quotes include design, permits and site works?
It varies by provider. Some bundle design, secondary dwelling permits and construction into a single turnkey figure. Others quote the build only and leave approvals and site preparation to you. Always ask directly which of the three is included. If permits are excluded, budget separately for council application fees, building surveyor costs and any reports the council requests. Site costs such as excavation, retaining and service connections are the most common omission, so get them itemised in writing.
How do I compare quotes from granny flat builders?
Put every quote into the same format before comparing totals. Build a table with columns for design, permits, site costs, slab and frame spec, inclusions, exclusions, provisional sums, timeline and warranty terms. Then compare line by line, not bottom line to bottom line. A cheaper quote often excludes items another builder includes. Ask each builder to confirm access requirements, service locations and whether their price assumes level ground. Like-for-like comparison is the only way to see the real gap.
What can make a granny flat construction quote more expensive?
Sloping blocks, poor rear access, and services that need rerouting are the biggest cost drivers. Heritage overlays, bushfire-prone land and flood zones can trigger extra reports and construction standards. Upgraded finishes, additional bathrooms and larger floor areas add cost too. Ask each builder which assumptions sit behind their price, then confirm whether your block meets them. If it does not, request a revised figure before signing rather than discovering the difference mid-build.
Getting a quote for secondary dwelling construction is straightforward once you know what to demand from it. The hard part is comparing quotes that were never written on the same basis. Granny X handles design, permits, construction and tenanting as one end-to-end service, with a 7-star NatHERS rated, concrete slab and timber frame build and direct access to your builder and project lead throughout. Book your free site assessment and get a quote you can actually compare.